EMBEDDING AND MAINTANCE
EMBEDDING AND MAINTANCE
Instalation of the unit with double surface – type AB
The pit must be excavated with corresponding ground dimensions and a concrete foundation board must be prepared (min. 20cm from the border of unit)
Settling of the separator consists of its placing on the flat concrete foundation board with an accuracy ± 5 mm (min. 25 cm of thickness), connecting to inlet and outlet pipes, filling the water into the unit 30 cm high and back filling with concrete. Filling with water and filling back with the concrete must be carried out concurrently until top of the tank.
On the top of the unit is necessary to concrete foundation board in accordance with the load.
Instalation of the unit with one surface – type SN
The pit must be excavated with corresponding ground dimensions and a concrete foundation board must be prepared (min. 40cm from the border of unit).
Settling of the separator consists of its placing on the flat concrete foundation board with an accuracy ± 5 mm (min. 25 cm of thickness), connecting to inlet and outlet pipes, filling the water into the unit 30 cm high and back filling the soil works.
Filling with water and filling back the soil works must be carried out concurrently until top of the tank.
Instalation of the unit with square cross section – type P (embedding to the grass area)
The pit must be excavated with corresponding ground dimensions and a concrete foundation board must be prepared (min. 40cm from the border of unit).
Settling of the separator consists of its placing on the flat concrete foundation board with an accuracy ± 5 mm (min. 25 cm of thickness), connecting to inlet and outlet pipes, filling the water into the unit 30 cm high and back filling the soil works.
Filling with water and filling back the soil works must be carried out concurrently until top of the tank.
Instalation of the unit with square cross section – type ER (embedding in road way, high level of subsoil water)
The pit must be excavated with corresponding ground dimensions and a concrete foundation board must be prepared (min. 20cm from the border of unit)
Settling of the separator consists of its placing on the flat concrete foundation board with an accuracy ± 5 mm (min. 25 cm of thickness), connecting to inlet and outlet pipes, filling the water into the unit 30 cm high and back filling with concrete. Filling with water and filling back with the concrete must be carried out concurrently until top of the tank.
On the top of the unit is necessary to concrete foundation board in accordance with the load.
Maintenance of the oil separators
Visual function check is necessary 1-2 times a month.
The operating staff checks the level of the water surface in all the parts of the separator, the condition of the sludge filters, the quantity of oil substances on a water surface.
This operation can be also done together with a sludge removal carried out by a special authorized company.
The liquidation of the removed oil substances must correspond with regulations concerning the waste liquidation. The oil substances have the character of a dangerous waste according to the law. Sorption filter is necessary to replace with new one.
Immediately after extracting the sludge, the separator must be refilled with water up to the original level.
Maintenance of the grease separators
Visual function check is necessary 1-2 times a month.
The operating staff checks the level of the water surface in all the parts of the separator, the condition of the sludge filters, the quantity of oil substances on a water surface.
This operation can be also done together with a sludge removal carried out by a special authorized company.
The liquidation of the removed oil substances must correspond with regulations concerning the waste liquidation. The oil substances have the character of a dangerous waste according to the law.
Immediately after extracting the sludge, the separator must be refilled with water up to the original level.
111 View Rd | Sunnyvale
Auckland 0612
New Zealand
Tel : +64 21/1931-777
E-Mail: info@bor-plastika.co.nz
*Bor-plastika is not responsible for any errors in the text
CROATIA
Bor-plastika d.o.o.
Glavna 26, Kneževi Vinogradi
Tel: +385 31/730-881
E-Mail: bor-plastika@bor-plastika.hr
SERBIA
Borplastikaeko d.o.o.
Janka Čmelika 26/101, Novi Sad
Tel: +381 21/6312-299
E-Mail: office@borplastikaeko.rs
BiH
Borplastikaeko d.o.o.
Aleja Alija Izetbegovića 31, Tuzla
Tel: +387 35/279-122
E-Mail: office@borplastikaeko.ba
MONTENEGRO
Borplastikaeko d.o.o.
Kozaračka 21a, 81000, Podgorica
Tel: +382 20/240 780
E-Mail: direktor@borplastikaeko.me
HUNGARY
Bolygó utca 18, Pécs
Tel: +36 72/891-363
E-mail: office@bor-plastika.eu
MACEDONIA
EHI dooel
3 Makedonska brigada bb , Skopje
Tel : +389 22/460-075
E-Mail: contact@ehi.com.mk
With pride, we bid farewell to another successful year marked by efforts, dedication, and achievements we have accomplished together.
Last Friday we have celebrated the official opening of our new complex of buildings for business and production purposes:
Another year has come to an end and we thank all our partners for their trust! We hope that we will cooperate equally successfully in the coming year.
Company Bor-Plastika is engaged in designing, mediation, consulting and manufacturing of wastewater treatment plants.
Leave a Comment